SMED change-over analysis

Change-over steps as internal or external, with a proposal per step: the new change-over time, the time saved, and the effect on EPEI and batch size.

Input

Paste, open a CSV, TSV, TXT or XLSX file (up to 20 MB), or drop it on the field. Files are read in this browser only.

Columns (6 possible, found by the header names)
Columns

Found by the header names, or in the order Step, Duration, Internal / external, Category, Action, New duration. Change them if they are wrong.

Step           Duration  Type      Category     Action               New duration
Fetch the die  12        Internal  Preparation  Convert to external  12
Mount the die  12        Internal  Mounting     Shorten              8
Long format
1 row = 1 step

Columns: tab, ; or ,
Decimals: 12,5 or 12.5

Paste measurements to start.

One row per step in the order observed. Type: Internal (machine stopped, the default) or External. Category: Preparation, Mounting, Measuring (setting, adjusting) or Trial. Action: Keep, Convert to external, Shorten (give the new duration) or Eliminate.

With the demand, the available time, the cycle time and the number of variants, the change-over time turns into EPEI (every part every interval) and the batch size of each variant, before and after. Leave all four empty to skip it.

Runs in this browser. Data is not uploaded or stored.

Results

—Change-over after
—Change-over before
—Saved per change-over
—Internal time reduction

    How the SMED analysis is calculated

    SMED (single-minute exchange of die) shortens a change-over by separating the work that needs the machine stopped from the work that can be done while it runs, moving as much as possible to the second kind, and then shortening what stays. The method is a common practice, not a standard; the categories and actions here are the usual ones.

    Formulas

    Worked example (the tool’s example)

    1. Eleven of the twelve steps of the die change are internal: 12 + 8 + 6 + 10 + 5 + 12 + 7 + 9 + 15 + 10 + 4 = 98 min of stop; returning the old die (8 min) is already external.
    2. Fetching the die, finding the tools and the paperwork (24 min) move to external; quick clamps, pins, couplings, shims and fewer trial parts shorten five steps; the fine adjustment is eliminated.
    3. Internal time after: 2 + 10 + 5 + 8 + 3 + 2 + 6 = 36 min, saving 62 min per change-over, a reduction of 63.3 %.
    4. 2400 pieces a day at 12 s take 480 min of the 960 available, leaving 480 min. With four variants EPEI = 4 × 98 / 480 = 0.82 days before and 4 × 36 / 480 = 0.30 days after; the batch of each variant drops from 490 to 180 pieces.

    Common mistakes

    Input and files

    Questions

    What is the difference between internal and external work?
    Internal work can only be done while the machine is stopped, such as taking out the old die. External work can be done while the machine still runs the previous order or already runs the next one, such as fetching the next die, preheating it or getting the tools ready. Only internal work adds to the change-over time.
    Where does SMED start?
    With watching and timing one real change-over step by step, ideally on video. Then mark each step internal or external, move everything possible to external, and only then shorten the internal steps (quick clamps, locating pins, standard heights, parallel work) and remove adjustments and trial runs. The blank observation sheet is made for the first part.
    What is EPEI and why does it get shorter?
    Every part every interval: how many periods (days, shifts) it takes to run every variant once. It is the number of change-overs in one round times the change-over time, divided by the time left after running the demand. A shorter change-over leaves the same free time for more change-overs, so every variant can be made more often in smaller batches, with less stock.
    Does a shorter change-over always mean smaller batches?
    Only if the saved time is used for more change-overs. It can also be used for more output, when the machine is a bottleneck. The tool shows the smaller batch it allows; whether to take it is a decision about stock against capacity.