Takt time calculator

Takt time from available time and customer demand, a planned cycle time with an efficiency factor, stations over takt and the minimum number of stations.

Input

The period is whatever the demand covers: one day (1 working day), a week (5) or a month. Other planned stops that are not production time, such as meetings or cleaning, belong in the breaks. The efficiency gives a planned cycle time below takt that leaves room for losses.

Paste, open a CSV, TSV, TXT or XLSX file (up to 20 MB), or drop it on the field. Files are read in this browser only.

Columns

Found by the header names, or in the order Station, Cycle time (s). Change them if they are wrong.

Station   Cycle time (s)
Kitting   41
Screwing  70.5
Long format
1 row = 1 station

Columns: tab, ; or ,
Decimals: 12,5 or 12.5

Paste measurements to start.

One row per station with its cycle time in seconds (the work done at the station for one unit). Without stations only takt is calculated.

Runs in this browser. Data is not uploaded or stored.

Results

—Takt time
—Planned cycle time
—Minimum stations
—Units per hour

    How takt time is calculated

    Takt time is the rate of customer demand turned into time: the available production time divided by the number of units the customer needs in the same period. If every station finishes its work within takt, the line makes what is needed without overproducing; a station slower than takt is a bottleneck before the first part is made.

    Formulas

    Worked example (the tool's example)

    1. Two shifts of 480 min with 30 min of breaks, 5 days: available time = 2 × (480 − 30) × 5 = 4500 min = 270,000 s.
    2. The customer needs 4000 units a week: takt = 270,000 / 4000 = 67.5 s, or 53.3 units per hour.
    3. With an efficiency of 85 % the planned cycle time is 67.5 × 0.85 = 57.38 s.
    4. The seven stations add up to 358 s of work: at least ⌈358 / 67.5⌉ = ⌈5.30⌉ = 6 stations at takt, ⌈358 / 57.375⌉ = ⌈6.24⌉ = 7 at the planned cycle time. The line has 7, so the balance is 358 / (7 × 67.5) = 75.8 %.
    5. Screwing takes 70.5 s, more than takt: the line can make at most ⌊270,000 / 70.5⌋ = 3829 units a week, short of 4000. Wiring (58.5 s) and function test (64 s) fit takt but not the planned cycle time.

    Common mistakes

    Input and files

    Questions

    What is the difference between takt time and cycle time?
    Takt time comes from the customer: the available time divided by the demand, the pace at which one unit must be finished. Cycle time comes from the process: how long a station or the line actually takes for one unit. A station whose cycle time is longer than takt cannot keep up with demand.
    Should the cycle time be equal to takt?
    No, a little below it. Breakdowns, changeovers, minor stops and rejects take time that takt does not include, so lines are usually planned to a cycle time of takt multiplied by an efficiency or OEE factor, for example 85 %.
    Are breaks part of the available time?
    No. Available time is the time the line is meant to produce: shift length minus breaks, and minus other planned stops such as meetings or cleaning. Unplanned stops are not taken off; they are covered by the efficiency factor.
    How many operators or stations do I need?
    At least the total work content divided by takt, rounded up. That is a lower bound: if the work cannot be split evenly, or the order of the tasks does not allow it, more stations are needed. The line balancing tool assigns tasks to stations with their precedence.