Takt time calculator

Takt time from available time and customer demand, a planned cycle time with an efficiency factor, stations over takt and the minimum number of stations.

Input

The period is whatever the demand covers: one day (1 working day), a week (5) or a month. Other planned stops that are not production time, such as meetings or cleaning, belong in the breaks. The efficiency gives a planned cycle time below takt that leaves room for losses.

Example dataReplace with your own station times

Paste, open a CSV, TSV, TXT or XLSX file (up to 20 MB), or drop it on the field. Files are read in this browser only.

Columns

Found by the header names, or in the order Station, Cycle time (s). Change them if they are wrong.

Station   Cycle time (s)
Kitting   41
Screwing  70.5
Long format
1 row = 1 station

Columns: tab, ; or ,
Decimals: 12,5 or 12.5

Read as: tab-separated · decimal point · 7 rows · header row skipped

Data as understood — 7 rows
#StationCycle time (s)
1Kitting41
2Pre-assembly55
3Screwing70.5
4Wiring58.5
5Function test64
6Labelling22
7Packing47

One row per station with its cycle time in seconds (the work done at the station for one unit). Without stations only takt is calculated.

Runs in this browser. Data is not uploaded or stored.

Results

67.50 sTakt time
57.38 sPlanned cycle time
6Minimum stations
53.3Units per hour

Takt 67.50 s = 270000 s available / demand · bottleneck Screwing 70.5 s → 3829 units in the period

  • 1 station is slower than takt (Screwing): the line cannot meet the demand without moving work, adding a parallel station or more time.
  • 2 stations are within takt but slower than the planned cycle time (Wiring, Function test): no room is left for the losses.
Cycle time of each station against takt 67.50 s, planned cycle time 57.38 s: Kitting 41.0 s; Pre-assembly 55.0 s; Screwing 70.5 s, over takt; Wiring 58.5 s, over the planned cycle time; Function test 64.0 s, over the planned cycle time; Labelling 22.0 s; Packing 47.0 s.0204060Cycle time (s)Kitting41.0Pre-assembly55.0Screwing70.5Wiring58.5Function test64.0Labelling22.0Packing47.0Takt 67.5 sPlanned 57.4 s
Within the planned cycleOver the planned cycleOver taktTaktPlanned cycle time
Takt
QuantityValue
Available time per period4500.0 min
Takt time67.50 s
Units per hour at takt53.3
Planned cycle time (takt × efficiency)57.38 s
Work content (Σ cycle times)358.0 s
Stations now7
Minimum stations at takt6
Minimum stations at the planned cycle7
Balance (work content / stations × takt)75.8%
Bottleneck output per period3829 units
Stations
StationCycle time (s)Share of taktState
Kitting41.060.7%OK
Pre-assembly55.081.5%OK
Screwing70.5104.4%Over takt
Wiring58.586.7%Over planned cycle
Function test64.094.8%Over planned cycle
Labelling22.032.6%OK
Packing47.069.6%OK

Download offline versionSingle HTML file · v1.2 · 549 KB · works without internet

How takt time is calculated

Takt time is the rate of customer demand turned into time: the available production time divided by the number of units the customer needs in the same period. If every station finishes its work within takt, the line makes what is needed without overproducing; a station slower than takt is a bottleneck before the first part is made.

Formulas

Worked example (the tool's example)

  1. Two shifts of 480 min with 30 min of breaks, 5 days: available time = 2 × (480 − 30) × 5 = 4500 min = 270,000 s.
  2. The customer needs 4000 units a week: takt = 270,000 / 4000 = 67.5 s, or 53.3 units per hour.
  3. With an efficiency of 85 % the planned cycle time is 67.5 × 0.85 = 57.38 s.
  4. The seven stations add up to 358 s of work: at least ⌈358 / 67.5⌉ = ⌈5.30⌉ = 6 stations at takt, ⌈358 / 57.375⌉ = ⌈6.24⌉ = 7 at the planned cycle time. The line has 7, so the balance is 358 / (7 × 67.5) = 75.8 %.
  5. Screwing takes 70.5 s, more than takt: the line can make at most ⌊270,000 / 70.5⌋ = 3829 units a week, short of 4000. Wiring (58.5 s) and function test (64 s) fit takt but not the planned cycle time.

Common mistakes

Input and files

Questions

What is the difference between takt time and cycle time?
Takt time comes from the customer: the available time divided by the demand, the pace at which one unit must be finished. Cycle time comes from the process: how long a station or the line actually takes for one unit. A station whose cycle time is longer than takt cannot keep up with demand.
Should the cycle time be equal to takt?
No, a little below it. Breakdowns, changeovers, minor stops and rejects take time that takt does not include, so lines are usually planned to a cycle time of takt multiplied by an efficiency or OEE factor, for example 85 %.
Are breaks part of the available time?
No. Available time is the time the line is meant to produce: shift length minus breaks, and minus other planned stops such as meetings or cleaning. Unplanned stops are not taken off; they are covered by the efficiency factor.
How many operators or stations do I need?
At least the total work content divided by takt, rounded up. That is a lower bound: if the work cannot be split evenly, or the order of the tasks does not allow it, more stations are needed. The line balancing tool assigns tasks to stations with their precedence.