Standard work combination table

Manual, machine and walk time of every work element on one time line against takt: operator cycle, machines the operator has to wait for, A3 print and Excel.

Input

Example dataReplace with your own elements

Paste, open a CSV, TSV, TXT or XLSX file (up to 20 MB), or drop it on the field. Files are read in this browser only.

Columns (4 possible, found by the header names)
Columns

Found by the header names, or in the order Work element, Manual (s), Machine (s), Walk (s). Change them if they are wrong.

Work element                  Manual    Machine   Walk
Load the welder and start it  8         48        4
Long format
1 row = 1 element

Columns: tab, ; or ,
Decimals: 12,5 or 12.5

Read as: tab-separated · whole numbers · 5 rows · header row skipped

Data as understood — 5 rows
#Work elementManual (s)Machine (s)Walk (s)
1Take a part from the rack43
2Load the welder and start it8484
3Deburr the welded part102
4Load the press and start it6123
5Inspect and pack95

One row per work element in the order the operator does them, times in seconds. Machine: the time the machine runs on its own after the operator started it (empty when none). Walk: to the next element.

Runs in this browser. Data is not uploaded or stored.

Results

54.0 sOperator cycle
58.0 sTakt
2.0 sLongest wait for a machine
56.0 sCycle with the wait

Operator cycle 54.0 s (manual 37.0 s, walk 17.0 s), within the takt of 58.0 s; waiting for a machine makes it 56.0 s.

  • The machine of “Load the welder and start it” runs until 63 s but the operator is back at 61 s: 2 s late.
  • The operator waits 2 s each cycle, for the machine of “Load the welder and start it” (the latest one); the cycle becomes 56 s.
Combination chart: operator cycle 54.0 s against takt 58.0 s; Take a part from the rack: manual 0.0–4.0 s, walk 3.0 s; Load the welder and start it: manual 7.0–15.0 s, machine to 63.0 s, walk 4.0 s, machine late 2.0 s; Deburr the welded part: manual 19.0–29.0 s, walk 2.0 s; Load the press and start it: manual 31.0–37.0 s, machine to 49.0 s, walk 3.0 s; Inspect and pack: manual 40.0–49.0 s, walk 5.0 s.010203040506070Seconds1. Take a part from the rack2. Load the welder and start it3. Deburr the welded part4. Load the press and start it5. Inspect and packTakt 58.0 sCycle 54.0 s
Manual: thick lineMachine: dashedWalk: wavyTakt: dash-dot
Work elements
ElementManual (s)Machine (s)Walk (s)Start (s)Machine end (s)Back (s)Late (s)
Take a part from the rack4.0—3.00.0—54.0—
Load the welder and start it8.048.04.07.063.061.02.0
Deburr the welded part10.0—2.019.0—73.0—
Load the press and start it6.012.03.031.049.085.0—
Inspect and pack9.0—5.040.0—94.0—

Download offline versionSingle HTML file · v1.5 · 550 KB · works without internet

Blank template to print or fill in your own program

How the combination table is calculated

The standard work combination table puts one operator’s round on a time line, element by element, together with the machines the operator starts. It is part of standard work as commonly practised (from the Toyota Production System), not a standard; the lines and checks here are the usual ones.

Formulas

Worked example (the tool’s example)

  1. Manual 4 + 8 + 10 + 6 + 9 = 37 s, walk 3 + 4 + 2 + 3 + 5 = 17 s: operator cycle 54 s.
  2. The welder is started at 7 + 8 = 15 s and runs 48 s, to 63 s; the operator is back at 7 + 54 = 61 s and waits 2 s: the cycle becomes 56 s.
  3. 56 s is within the takt of 58 s; the press (37 to 49 s, operator back at 85 s) is never waited for.

Common mistakes

Input and files

Questions

What is a standard work combination table?
A chart of one operator’s work elements on a time line: manual work as a solid line, the time a machine runs on its own as a dashed line, walking as a wavy line, and the takt as a line across. It shows at a glance whether the operator’s cycle fits the takt and whether the machines are ready when the operator comes back to them.
Why does the operator wait for a machine?
A machine started in one element runs while the operator does the rest of the round. If its machine time is longer than the time until the operator comes back, one cycle later, the operator stands and waits. The table shows for every machine how late it is; the operator waits once per cycle, for the latest machine (after that wait the others are ready in time), so the cycle becomes the operator’s cycle plus the longest lateness.
Is walking time waste?
It adds no value, but it is part of the cycle as long as the layout needs it. Showing it as its own line makes it visible: moving a rack or a machine closer often shortens the cycle more than working faster.